SAIL’s Strategic Surge & SMS’s Synchronized Solution

SMS group modernizes SAIL Durgapur’s billet casters with a turnkey contract. The project upgrades two 6-strand machines from a six-meter to seven-meter radius. Output increases by 60% using existing foundations. Execution occurs within five-month shutdown windows per caster, with commissioning scheduled for 2027 & 2028.